Littles Manor Farm (9.5 MW solar farm)

Littles Manor Farm is a 9.5 MW solar farm project in Swale, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 7 May 2014; the record was last updated on 25 November 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.5 MWsolar farm
refused on appealstatus in REPD
25 November 2014record last updated
Swalecouncil area

Planning timeline

DateStage
19 July 2013Application submitted
22 November 2013Refused by the planning authority
5 February 2014Appeal lodged
7 May 2014Appeal refused

Project details

Technology
solar farm
Capacity
9.5 MW
Status (REPD)
refused on appeal
Record last updated
25 November 2014
Operator or applicant
The Landmark Practice
Planning authority
Swale
Planning application reference
SW/13/0832
Appeal reference
APP/V2255/A/14/2212592
Site area
19.6 ha
Address (REPD)
Littles Manor Farm, Ashford Road, Sheldwich, Faversham, Kent
Council area (by location)
Swale
Time to decision
18 weeks
REPD reference
2293

Who decides

ApplicationsSwaleUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused4 of 3012%
Onshore wind refused1 of 345%
Battery storage refused0 of 716%
Median time from submission to decision15.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Abbey Fields Farmsolar farm5.3operational3.6
Cleve Hill Solar Projectsolar farm373operational5.9
North Court Farm, Chilham Solar Farmsolar farm44refused on appeal7.4
Pitstock Farmsolar farm41approved, not built9.4
Plot 2B EurolinkVbattery storage20under construction10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2898, 0.8806).