Abbey Fields Farm (5.3 MW solar farm)

Abbey Fields Farm is a 5.3 MW solar farm project in Swale, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2016; the record was last updated on 3 October 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.3 MWsolar farm
operationalstatus in REPD
3 October 2016record last updated
Swalecouncil area

Planning timeline

DateStage
8 July 2015Application submitted
30 October 2015Planning permission granted
30 January 2016Construction started
30 March 2016Operational

Project details

Technology
solar farm
Capacity
5.3 MW
Status (REPD)
operational
Record last updated
3 October 2016
Operator or applicant
FR Solar Kent PV
Planning authority
Swale
Planning application reference
15/505437/FULL
Site area
9.7 ha
Address (REPD)
Abbey Fields Farm, Abbey Fields, Faversham, Kent
Council area (by location)
Swale
Time to decision
16 weeks
REPD reference
5394

Who decides

ApplicationsSwaleUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused4 of 3012%
Onshore wind refused1 of 345%
Battery storage refused0 of 716%
Median time from submission to decision15.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cleve Hill Solar Projectsolar farm373operational2.4
Littles Manor Farmsolar farm9.5refused on appeal3.6
North Court Farm, Chilham Solar Farmsolar farm44refused on appeal8.4
Old Rides solar Farmsolar farm8operational8.6
New Rides Wind Farmwind farm8.8operational9.0
Old Rides Farm, Leysdown Roadbattery storage1,000application submitted9.2
New Rides Farm - Photovoltaic Panelssolar farm10approved, not built9.2
Tonge Corner Farmsolar farm22operational9.4
Plot 2B EurolinkVbattery storage20under construction9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3187, 0.9029).