Renewable energy projects in Ashford
35 solar, wind or battery projects of 150 kW or more are located in Ashford (REPD, July 2026 extract): 3 pending, 21 approved but not running, 5 operational and 5 refused. The council refused 8 of 30 decided applications (27%; UK 19%), with a median 13 weeks from submission to decision.
35projects in the council area
3awaiting a decision
21approved, not running
27%of decisions refused
How Ashford decides
| Applications | Ashford | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 30 | 10,236 |
| Refused | 8 (27%) | 19% |
| Solar refused | 6 of 21 | 12% |
| Battery storage refused | 2 of 9 | 16% |
| Median time from submission to decision | 12.7 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 2 | — |
Projects in Ashford
Projects of 1 MW and more (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated |
|---|---|---|---|---|---|---|
| Forty Acre Wood, The Streetbattery storage | battery storage | 300 | refusedupdated Dec 2025 | Jul 2025 | refused Oct 2025 | Dec 2025 |
| Stonestreet Green Solar Farm & Battery Storagesolar farm | solar farm | 99.9 | approved, not builtupdated Nov 2025 | Jul 2024 | granted Oct 2025 | Nov 2025 |
| Sellindge Substation, Church Lanebattery storage | battery storage | 57 | approved, not builtupdated Sep 2023 | Sep 2022 | granted Aug 2023 | Sep 2023 |
| East Stour Solar Farmsolar farm | solar farm | 49.9 | application submitted may be out of dateupdated Jul 2022 | Jun 2022 | — | Jul 2022 |
| North Court Farm, Chilham Solar Farmsolar farm | solar farm | 44 | refused on appealupdated May 2024 | Oct 2022 | refused Apr 2024 | May 2024 |
| Appledore Road, Kenardington Solar Farmsolar farm | solar farm | 35 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 |
| Partridge Farmsolar farm | solar farm | 10.6 | operationalupdated Apr 2016 | Apr 2014 | granted Oct 2015 | Apr 2016 |
| Land South of Dowle Streetsolar | solar | 9 | refused on appealupdated Aug 2015 | Jul 2013 | refused Feb 2014 | Aug 2015 |
| Kenardington Place Farmsolar farm | solar farm | 7 | operationalupdated Sep 2015 | Oct 2013 | granted Sep 2014 | Sep 2015 |
| Oaklands Farmsolar farm | solar farm | 6.9 | operationalupdated May 2015 | Mar 2014 | granted Jun 2014 | May 2015 |
| Premier Grocery Products, Kennington Roadrooftop solar | rooftop solar | 2.1 | approved, not builtupdated May 2025 | Jan 2025 | granted Mar 2025 | May 2025 |
Smaller schemes under 1 MW, mostly rooftop solar (24)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated |
|---|---|---|---|---|---|---|
| CCL Label, Foster Roadrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Aug 2024 | May 2024 | granted Jul 2024 | Aug 2024 |
| Warren Retail Park, J Sainsburyrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Jan 2026 | Sep 2025 | granted Oct 2025 | Jan 2026 |
| Ashford Cold Store Ardo Shearway Limited, Ashford Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Mar 2025 | Jan 2025 | granted Jan 2025 | Mar 2025 |
| William Harvey Hospitalsolar farm | solar farm | 0.4 | operationalupdated Jan 2021 | Jul 2019 | granted Oct 2020 | Jan 2021 |
| John Lewis At Home, Fougeres Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Oct 2023 | Jul 2023 | granted Sep 2023 | Oct 2023 |
| Tesco Moatfield Meadowrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2019 | Dec 2018 | granted Feb 2019 | Feb 2019 |
| Balfour Beatty Rail Plant, Old Railway Worksrooftop solar | rooftop solar | 0.3 | refusedupdated Jan 2026 | Sep 2025 | refused Oct 2025 | Jan 2026 |
| The Cold Store, Swan Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2022 | Sep 2022 | granted Oct 2022 | Mar 2022 |
| Wembdon Business Centre, Bower Road Solar Arrayssolar farm | solar farm | 0.2 | approved, not builtupdated Feb 2024 | Nov 2023 | granted Jan 2024 | Feb 2024 |
| Stanhope Road, Kingsnorth - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Mar 2025 | Oct 2024 | granted Mar 2025 | Mar 2025 |
| Church Road, Sevington Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Mar 2025 | Nov 2024 | granted Mar 2025 | Mar 2025 |
| Ashford Road, Kingsnorth Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Mar 2025 | Nov 2024 | granted Jan 2025 | Mar 2025 |
| Sandyhurst Lane, Boughton Aluph Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Nov 2025 | Nov 2024 | granted Jul 2025 | Nov 2025 |
| Stanhope Road, Kingsnorth - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | application submittedupdated Jan 2025 | Oct 2024 | — | Jan 2025 |
| Cobbs Wood Industrial Estate, Chart Roadbattery storage | battery storage | 0.2 | approved, not builtupdated May 2026 | Nov 2025 | granted Apr 2026 | May 2026 |
| Hornbeam Close - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated May 2026 | Nov 2025 | granted Mar 2026 | May 2026 |
| Singleton Hill, Singleton - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | application withdrawnupdated Feb 2026 | Nov 2025 | — | Feb 2026 |
| Loudon Way, Repton Park Southbattery storage | battery storage | 0.2 | refusedupdated Mar 2026 | Dec 2025 | refused Feb 2026 | Mar 2026 |
| Consort Frozen Foods Limited, Wotton Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Jun 2023 | Aug 2023 |
| Ashford Cattle Market Co, Monument Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Jun 2023 | granted Jul 2023 | Sep 2023 |
| Station Roadrooftop solar | rooftop solar | 0.2 | operationalupdated Nov 2023 | Dec 2021 | granted Mar 2022 | Nov 2023 |
| Newtown Road Solar Panels & Air Source Heat Pumpsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2022 | Jun 2022 | granted Mar 2023 | Jul 2022 |
| Stonestreet Green Solar Farm & Battery Storagebattery storage | battery storage | — | approved, not builtupdated Nov 2025 | Jul 2024 | granted Oct 2025 | Nov 2025 |
| Wyvern Way, Henwood Industrial Estaterooftop solar | rooftop solar | — | approved, not builtupdated Feb 2023 | Jan 2023 | granted Feb 2023 | Feb 2023 |
Postcode districts in Ashford
| District | Projects within 10 km | Pending | Approved | Operational |
|---|---|---|---|---|
| TN23 | 33 | 3 | 21 | 5 |
| TN24 | 32 | 2 | 21 | 4 |
| TN25 | 30 | 3 | 19 | 4 |
| TN26 | 27 | 2 | 17 | 4 |
| TN27 | 10 | 0 | 3 | 2 |
| TN30 | 3 | 1 | 1 | 1 |
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Ashford by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.