Energy Projects Near You

East Stour Solar Farm (49.9 MW)

East Stour Solar Farm is a 49.9 MW solar farm project in Ashford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 27 June 2022, no decision recorded; the record was last updated on 12 July 2022. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
application submittedmay be out of datestatus in REPD
12 July 2022record last updated
Ashfordcouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
27 June 2022Application submitted

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
12 July 2022
Operator or applicant
EDF Energy Renewables
Planning authority
Ashford
Planning application reference
22/00668/AS
Site area
103.9 ha
Address (REPD)
Land south of M20 and south of railway line to the east and west of, Church Lane, Aldington
Council area (by location)
Ashford
REPD reference
9402

Who decides

ApplicationsAshfordUK
Decided applications (solar, wind, battery)3010,236
Refused8 (27%)19%
Solar refused6 of 2112%
Battery storage refused2 of 916%
Median time from submission to decision12.7 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Partridge Farmsolar farm10.6operational1.1
Sellindge Substation, Church Lanebattery storage57approved, not built1.4
Harringe Brooks Wind Parkwind farm15application submitted2.3
Stonestreet Green Solar Farm & Battery Storagesolar farm99.9approved, not built2.4
Forty Acre Wood, The Streetbattery storage300refused5.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0929, 0.9711).