Forty Acre Wood, The Street (300 MW battery storage)

Forty Acre Wood, The Street is a 300 MW battery storage project in Ashford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 27 October 2025; the record was last updated on 9 December 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

300 MWbattery storage
refusedstatus in REPD
9 December 2025record last updated
Ashfordcouncil area

Planning timeline

DateStage
29 July 2025Application submitted
27 October 2025Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
300 MW
Status (REPD)
refused
Record last updated
9 December 2025
Operator or applicant
Greenfield Energy Developments Limited
Planning authority
Ashford
Planning application reference
PA/2025/1331
Address (REPD)
E/O Forty Acre Wood, S/O Daffodil Cottage, The Street, Brabourne, Ashford
Council area (by location)
Ashford
Time to decision
13 weeks
Name in REPD
Forty Acre Wood, The Street - Battery Energy Storage System
REPD reference
19136

Who decides

ApplicationsAshfordUK
Decided applications (solar, wind, battery)3010,236
Refused8 (27%)19%
Solar refused6 of 2112%
Battery storage refused2 of 916%
Median time from submission to decision12.7 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sellindge Substation, Church Lanebattery storage57approved, not built4.0
Partridge Farmsolar farm10.6operational4.3
Harringe Brooks Wind Parkwind farm15application submitted5.3
East Stour Solar Farmsolar farm49.9application submitted5.4
Stonestreet Green Solar Farm & Battery Storagesolar farm99.9approved, not built5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1362, 1.0053).