Energy Projects Near You

Kenardington Place Farm (7 MW solar farm)

Kenardington Place Farm is a 7 MW solar farm project in Ashford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 30 September 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
operationalstatus in REPD
30 September 2015record last updated
Ashfordcouncil area

Planning timeline

DateStage
7 October 2013Application submitted
23 January 2014Refused by the planning authority
15 September 2014Planning permission granted
15 September 2014Appeal allowed
1 January 2015Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
operational
Record last updated
30 September 2015
Operator or applicant
Kronos Solar
Planning authority
Ashford
Planning application reference
13/01074/AS
Site area
14.4 ha
Address (REPD)
Kenardington Place Farm, Appledore Road, Kenardington, Ashford, Kent, TN26 2LZ
Council area (by location)
Ashford
Time to decision
49 weeks
REPD reference
2138

Who decides

ApplicationsAshfordUK
Decided applications (solar, wind, battery)3010,236
Refused8 (27%)19%
Solar refused6 of 2112%
Battery storage refused2 of 916%
Median time from submission to decision12.7 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Appledore Road, Kenardington Solar Farmsolar farm35application submitted1.4
Martin Farm, St. Marys Roadsolar farm16approved, not built7.6
St Mary in the Marshsolar farm16application submitted7.6
Sycamore Farmsolar farm20operational8.8
Stonestreet Green Solar Farm & Battery Storagesolar farm99.9approved, not built10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0612, 0.8125).