Energy Projects Near You

Britton Court Farm, Hackington Road Solar Farm (38 MW)

Britton Court Farm, Hackington Road Solar Farm is a 38 MW solar farm project in Canterbury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 July 2025, not yet built; the record was last updated on 28 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

38 MWsolar farm
approved, not builtstatus in REPD
28 July 2025record last updated
Canterburycouncil area

Planning timeline

DateStage
20 September 2024Application submitted
4 July 2025Planning permission granted
4 July 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
38 MW
Status (REPD)
approved, not built
Record last updated
28 July 2025
Operator or applicant
Renewable Connections Developments Limited
Planning authority
Canterbury
Planning application reference
CA/24/02283
Site area
79.0 ha
Address (REPD)
Britton Court Farm, Hackington Road, Tyler Hill, Canterbury
Council area (by location)
Canterbury
Time to decision
41 weeks
Name in REPD
Britton Court Farm, Hackington Road - Solar Farm
REPD reference
17454

Who decides

ApplicationsCanterburyUK
Decided applications (solar, wind, battery)2610,236
Refused2 (8%)19%
Solar refused1 of 2112%
Battery storage refused1 of 516%
Median time from submission to decision12.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Woodlands Farm Solar Parksolar farm10operational3.8
Thanet Way, Herne Bay Solar Farmsolar farm20permission expired4.3
Woodlands Farm, Calcott Hillbattery storage228approved, not built4.4
Owls Hatch Roadsolar farm48operational4.6
Owls Hatch Road, Thanet Waybattery storage50approved, not built4.6
Molehill Farmsolar farm18operational4.8
Littlebournesolar farm17operational6.7
Nackington Farm Solar Park- Site Bsolar farm16.6application withdrawn7.4
Nackington Farm Solar Park- Site Csolar farm12application withdrawn7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.314, 1.0723).