Owls Hatch Road, Thanet Way (50 MW battery storage)

Owls Hatch Road, Thanet Way is a 50 MW battery storage project in Canterbury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 3 July 2025, not yet built; the record was last updated on 29 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
approved, not builtstatus in REPD
29 July 2025record last updated
Canterburycouncil area

Planning timeline

DateStage
19 December 2024Application submitted
3 July 2025Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
29 July 2025
Operator or applicant
Root Power South Limited
Planning authority
Canterbury
Planning application reference
CA/24/02262
Address (REPD)
R/O Share & Coulter Owls Hatch Road, S/O Thanet Way, Herne Bay
Council area (by location)
Canterbury
Time to decision
28 weeks
Name in REPD
Owls Hatch Road, Thanet Way - Battery Energy Storage Facility
REPD reference
18017

Who decides

ApplicationsCanterburyUK
Decided applications (solar, wind, battery)2610,236
Refused2 (8%)19%
Solar refused1 of 2112%
Battery storage refused1 of 516%
Median time from submission to decision12.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Owls Hatch Roadsolar farm48operational0.3
Thanet Way, Herne Bay Solar Farmsolar farm20permission expired0.5
Molehill Farmsolar farm18operational0.8
Woodlands Farm, Calcott Hillbattery storage228approved, not built3.4
Woodlands Farm Solar Parksolar farm10operational3.7
Britton Court Farm, Hackington Road Solar Farmsolar farm38approved, not built4.6
Marley Lane Solar Farm & Battery Storagesolar farm49.9refused6.7
Littlebournesolar farm17operational9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3528, 1.0952).