Marley Lane Solar Farm & Battery Storage (49.9 MW)

Marley Lane Solar Farm & Battery Storage is a 49.9 MW solar farm project in Canterbury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 8 December 2025; the record was last updated on 26 January 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
refusedstatus in REPD
26 January 2026record last updated
Canterburycouncil area

Planning timeline

DateStage
27 March 2025Application submitted
8 December 2025Refused by the planning authority

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
refused
Record last updated
26 January 2026
Operator or applicant
Enso Energy Limited
Planning authority
Canterbury
Planning application reference
CA/25/00570
Site area
94.4 ha
Address (REPD)
Land South Of Marley Lane Hoath
Council area (by location)
Canterbury
Time to decision
37 weeks
REPD reference
8892

The scheme also includes battery storage, recorded separately in REPD (refused).

Who decides

ApplicationsCanterburyUK
Decided applications (solar, wind, battery)2610,236
Refused2 (8%)19%
Solar refused1 of 2112%
Battery storage refused1 of 516%
Median time from submission to decision12.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Woodlands Farm, Calcott Hillbattery storage228approved, not built3.9
Woodlands Farm Solar Parksolar farm10operational4.4
Owls Hatch Roadsolar farm48operational6.5
Owls Hatch Road, Thanet Waybattery storage50approved, not built6.7
Thanet Way, Herne Bay Solar Farmsolar farm20permission expired7.1
Littlebournesolar farm17operational7.1
Molehill Farmsolar farm18operational7.5
Britton Court Farm, Hackington Road Solar Farmsolar farm38approved, not built8.2
Minster Abbey, Bedlam Court Lanesolar farm33under construction9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3318, 1.1862).