Energy Projects Near You

Littlebourne (17 MW solar farm)

Littlebourne is a 17 MW solar farm project in Canterbury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 13 November 2014; the record was last updated on 5 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17 MWsolar farm
operationalstatus in REPD
5 March 2015record last updated
Canterburycouncil area

Planning timeline

DateStage
2 October 2013Application submitted
8 January 2014Planning permission granted
1 July 2014Construction started
13 November 2014Operational

Project details

Technology
solar farm
Capacity
17 MW
Status (REPD)
operational
Record last updated
5 March 2015
Operator or applicant
Bluefield Solar Income Fund
Planning authority
Canterbury
Planning application reference
CA//13/01750
Site area
22.1 ha
Address (REPD)
Elbridge farm, Stturry, Cantenbury, Kent
Council area (by location)
Canterbury
Time to decision
14 weeks
REPD reference
2379

Who decides

ApplicationsCanterburyUK
Decided applications (solar, wind, battery)2610,236
Refused2 (8%)19%
Solar refused1 of 2112%
Battery storage refused1 of 516%
Median time from submission to decision12.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Nackington Farm Solar Park- Site Asolar farm11application withdrawn4.6
Nackington Farm Solar Park- Site Bsolar farm16.6application withdrawn4.9
Nackington Farm Solar Park- Site Csolar farm12application withdrawn4.9
Woodlands Farm Solar Parksolar farm10operational5.9
Woodlands Farm, Calcott Hillbattery storage228approved, not built6.5
Britton Court Farm, Hackington Road Solar Farmsolar farm38approved, not built6.7
Marley Lane Solar Farm & Battery Storagesolar farm49.9refused7.1
Chapmans Hillsolar7application withdrawn7.4
Snowdown Collierysolar farm5permission expired8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2738, 1.1439).