Energy Projects Near You

Owls Hatch Road (48 MW solar farm)

Owls Hatch Road is a 48 MW solar farm project in Canterbury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 March 2015; the record was last updated on 3 October 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

48 MWsolar farm
operationalstatus in REPD
3 October 2016record last updated
Canterburycouncil area

Planning timeline

DateStage
22 August 2014Application submitted
30 January 2015Planning permission granted
1 February 2015Construction started
29 March 2015Operational

Project details

Technology
solar farm
Capacity
48 MW
Status (REPD)
operational
Record last updated
3 October 2016
Operator or applicant
Cubico Sustainable Investments
Planning authority
Canterbury
Planning application reference
CA//14/01792
Address (REPD)
Land south of Owl's Hatch Road, Herne
Council area (by location)
Canterbury
Time to decision
23 weeks
REPD reference
2255

Who decides

ApplicationsCanterburyUK
Decided applications (solar, wind, battery)2610,236
Refused2 (8%)19%
Solar refused1 of 2112%
Battery storage refused1 of 516%
Median time from submission to decision12.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Owls Hatch Road, Thanet Waybattery storage50approved, not built0.3
Thanet Way, Herne Bay Solar Farmsolar farm20permission expired0.7
Molehill Farmsolar farm18operational1.1
Woodlands Farm, Calcott Hillbattery storage228approved, not built3.1
Woodlands Farm Solar Parksolar farm10operational3.4
Britton Court Farm, Hackington Road Solar Farmsolar farm38approved, not built4.6
Marley Lane Solar Farm & Battery Storagesolar farm49.9refused6.5
Littlebournesolar farm17operational9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3516, 1.0986).