Langenhoe Solar Farm (21.3 MW)

Langenhoe Solar Farm is a 21.3 MW solar farm project in Colchester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 4 March 2015; the record was last updated on 17 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21.3 MWsolar farm
operationalstatus in REPD
17 March 2015record last updated
Colchestercouncil area

Planning timeline

DateStage
22 November 2013Application submitted
29 August 2014Planning permission granted
8 September 2014Construction started
4 March 2015Operational

Project details

Technology
solar farm
Capacity
21.3 MW
Status (REPD)
operational
Record last updated
17 March 2015
Operator or applicant
NextEnergy Solar Fund
Planning authority
Colchester
Planning application reference
132330
Address (REPD)
Langenhoe Hall, Langenhoe, Colchester
Council area (by location)
Colchester
Time to decision
40 weeks
REPD reference
1463

Who decides

ApplicationsColchesterUK
Decided applications (solar, wind, battery)2410,236
Refused2 (8%)19%
Solar refused1 of 1912%
Battery storage refused1 of 516%
Median time from submission to decision13.3 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Holmwood Solar Farmsolar farm19refused on appeal3.3
Bluegates Solar Parksolar farm10.5operational7.0
Layer Farm Solar Farmsolar farm49operational7.2
Land Adjacent Claypits Farm (a)solar farm5operational9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8141, 0.9368).