Energy Projects Near You

Solar, wind and battery projects near Saffron Walden (CB10)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CB10 (Uttlesford): 5 approved but not yet running, 1 operational. The largest live scheme is Thaxted Solar farm (40 MW solar farm, approved on 29 September 2022, not yet built), 8.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
0awaiting a decision
5approved, not running
1operational

Projects within 10 km of CB10

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Butlers Farmsolar farmsolar farm7.7refused on appealupdated Apr 2016Sep 2014refused Mar 2015Apr 2016Uttlesford1.7
Long Meadow Solar Farmsolar farmsolar farm19operationalupdated Jul 2025Jan 2021granted Apr 2023Jul 2025Uttlesford2.9
Chesterford Park - Green Energy Hubsolar farmsolar farm2.8approved, not built may be out of dateupdated Sep 2021Sep 2021granted Dec 2022Sep 2021Uttlesford4.0
Little Linton Farmwind farmwind farm16refused on appealupdated Sep 2011Mar 2009refused Jun 2009Sep 2011South Cambridgeshire8.3
Thaxted Solar farmsolar farmsolar farm40approved, not builtupdated Jan 2024Jun 2021granted Sep 2022Jan 2024Uttlesford8.7
Abbey Farmsolar farmsolar farm5application withdrawnupdated May 2016Oct 2015—May 2016South Cambridgeshire9.1
Rectory Farmsolar farmsolar farm5application withdrawnupdated May 2016Oct 2015—May 2016South Cambridgeshire9.4
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Chesterford Park - Green Energy Hubbattery storagebattery storage—approved, not built may be out of dateupdated Sep 2021Sep 2021granted Dec 2022Sep 2021Uttlesford3.6
Dalehead Foods, Lintonrooftop solarrooftop solar0.9approved, not builtupdated Dec 2023Oct 2023granted Dec 2023Dec 2023South Cambridgeshire8.4
Thaxted Solar farmbattery storagebattery storage—approved, not builtupdated Jan 2024Jun 2021granted Sep 2022Jan 2024Uttlesford8.7

Distance from the average position of the CB10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm6021142.8
Rooftop solar101000.9
Wind farm100010
Battery storage202000

MW in pipeline: pending, approved and under-construction capacity.

How Uttlesford decides solar, wind and battery applications

ApplicationsUttlesfordUK
Decided applications (solar, wind, battery)3510,236
Refused11 (31%)19%
Solar refused7 of 2412%
Battery storage refused4 of 1116%
Median time from submission to decision20.0 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Essex, Uttlesford.

All projects in Uttlesford

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CB10, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.