Little Linton Farm (16 MW wind farm)

Little Linton Farm is a 16 MW wind farm project in South Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 27 October 2010; the record was last updated on 12 September 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16 MWwind farm
refused on appealstatus in REPD
12 September 2011record last updated
South Cambridgeshirecouncil area

Planning timeline

DateStage
4 March 2009Application submitted
25 June 2009Refused by the planning authority
27 October 2010Appeal refused

Project details

Technology
wind farm
Capacity
16 MW
Status (REPD)
refused on appeal
Record last updated
12 September 2011
Operator or applicant
Enertrag UK
Planning authority
South Cambridgeshire
Planning application reference
S/0232/09/F
Appeal reference
APP/W0530/A/09/2108277
Turbines
8
Address (REPD)
Cambridge Road, Linton, Cambridge. CB21 4JD
Council area (by location)
South Cambridgeshire
Time to decision
16 weeks
REPD reference
3518

Who decides

ApplicationsSouth CambridgeshireUK
Decided applications (solar, wind, battery)4810,236
Refused10 (21%)19%
Solar refused6 of 4012%
Onshore wind refused4 of 545%
Battery storage refused0 of 316%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Butlers Farmsolar farm7.7refused on appeal6.8
Sawston Solar Farm (Land North of Dales Manor Business Park)solar farm14refused on appeal6.9
Wadlow Wind Farmwind farm26operational7.7
Abbey Farmsolar farm5application withdrawn8.8
Great Wilbraham Solar Farmsolar farm38.1operational9.0
Rectory Farmsolar farm5application withdrawn9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1036, 0.2684).