Wadlow Wind Farm (26 MW)

Wadlow Wind Farm is a 26 MW wind farm project in South Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 September 2012; the record was last updated on 30 September 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

26 MWwind farm
operationalstatus in REPD
30 September 2016record last updated
South Cambridgeshirecouncil area

Planning timeline

DateStage
15 May 2006Application submitted
6 June 2007Refused by the planning authority
9 November 2009Planning permission granted
9 November 2009Appeal allowed
1 August 2011Construction started
1 September 2012Operational

Project details

Technology
wind farm
Capacity
26 MW
Status (REPD)
operational
Record last updated
30 September 2016
Operator or applicant
DIF
Planning authority
South Cambridgeshire
Planning application reference
S/1018/06/F
Turbines
13
Address (REPD)
Nr West Wratting, South Cambridgeshire
Council area (by location)
South Cambridgeshire
Time to decision
182 weeks
REPD reference
3935

Who decides

ApplicationsSouth CambridgeshireUK
Decided applications (solar, wind, battery)4810,236
Refused10 (21%)19%
Solar refused6 of 4012%
Onshore wind refused4 of 545%
Battery storage refused0 of 316%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Great Wilbraham Solar Farmsolar farm38.1operational3.8
Newmarket Road, Bottishamsolar farm49.9approved, not built6.0
Little Linton Farmwind farm16refused on appeal7.7
Exningsolar farm29.9operational9.6
Sawston Solar Farm (Land North of Dales Manor Business Park)solar farm14refused on appeal9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.166, 0.316).