Exning (29.9 MW solar farm)

Exning is a 29.9 MW solar farm project in East Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 27 March 2015; the record was last updated on 2 February 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29.9 MWsolar farm
operationalstatus in REPD
2 February 2017record last updated
East Cambridgeshirecouncil area

Planning timeline

DateStage
22 October 2013Application submitted
4 July 2014Planning permission granted
1 November 2014Construction started
27 March 2015Operational

Project details

Technology
solar farm
Capacity
29.9 MW
Status (REPD)
operational
Record last updated
2 February 2017
Operator or applicant
Vortex (formerly Sun Edison)
Planning authority
East Cambridgeshire
Planning application reference
13/00878/ESF
Site area
61.6 ha
Address (REPD)
Land Off Heath Road, Burwell
Council area (by location)
East Cambridgeshire
Time to decision
36 weeks
REPD reference
1913

Who decides

ApplicationsEast CambridgeshireUK
Decided applications (solar, wind, battery)3010,236
Refused1 (3%)19%
Solar refused0 of 2212%
Battery storage refused1 of 816%
Median time from submission to decision15.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land Southwest of Hightown Drove, Burwellbattery storage90refused2.9
Reach Roadbattery storage49.9approved, not built3.0
Long Barrow Solar Farm Projectsolar farm49.9application submitted3.4
Weirs Drove, Burwellbattery storage30application submitted3.6
Burwellbattery storage50operational3.9
Forest Heath Solar Farmsolar farm5operational4.4
Breach Farm Solar farmsolar farm67operational4.6
Burwell Solar Farmsolar farm49.9under construction4.8
Anchor Lane, Burwellbattery storage50approved, not built5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2502, 0.3486).