Weirs Drove, Burwell is a 30 MW battery storage project in East Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 26 May 2021, no decision recorded; the record was last updated on 6 July 2021. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.
application submittedmay be out of datestatus in REPD
6 July 2021record last updated
East Cambridgeshirecouncil area
application
approved
under construction
operational
The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.
Planning timeline
Date
Stage
26 May 2021
Application submitted
Project details
Technology
battery storage (stand-alone storage)
Capacity
30 MW
Status (REPD)
application submitted
Record last updated
6 July 2021
Operator or applicant
Fen Power 1 Limited
Planning authority
East Cambridgeshire
Planning application reference
21/00816/FUL
Address (REPD)
Land North Of Electricity Sub-Station Weirs Drove Burwell, Cambridge
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2744, 0.3144).