Energy Projects Near You

Goosehall Solar Farm (39.5 MW)

Goosehall Solar Farm is a 39.5 MW solar farm project in East Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 18 August 2020; the record was last updated on 1 December 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

39.5 MWsolar farm
operationalstatus in REPD
1 December 2021record last updated
East Cambridgeshirecouncil area

Planning timeline

DateStage
3 July 2015Application submitted
10 November 2015Planning permission granted
14 February 2020Construction started
18 August 2020Operational

Project details

Technology
solar farm
Capacity
39.5 MW
Status (REPD)
operational
Record last updated
1 December 2021
Operator or applicant
Lightsource Renewable Energy
Planning authority
East Cambridgeshire
Planning application reference
15/00723/ESF
Address (REPD)
New Fen Farm, Factory Road, Burwell, Cambridge, Cambridgeshire
Council area (by location)
East Cambridgeshire
Time to decision
19 weeks
REPD reference
5411

Who decides

ApplicationsEast CambridgeshireUK
Decided applications (solar, wind, battery)3010,236
Refused1 (3%)19%
Solar refused0 of 2212%
Battery storage refused1 of 816%
Median time from submission to decision15.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Burwell Anchor Lane Farm, Newnham Drovesolar farm50approved, not built0.1
Goose Hall Solar Farmsolar farm5approved, not built0.8
Anchor Lane, Burwellbattery storage50approved, not built0.9
Burwell Solar Farmsolar farm49.9under construction1.1
Burwellbattery storage50operational1.7
Weirs Drove, Burwellbattery storage30application submitted2.1
Long Barrow Solar Farm Projectsolar farm49.9application submitted2.1
Land Southwest of Hightown Drove, Burwellbattery storage90refused2.6
Reach Roadbattery storage49.9approved, not built2.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2931, 0.3098).