Energy Projects Near You

Goose Hall Solar Farm (5 MW)

Goose Hall Solar Farm is a 5 MW solar farm project in East Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 March 2021, not yet built; the record was last updated on 1 September 2021. REPD also records that the planning permission expired on 19 March 2024, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
approved, not builtmay be out of datestatus in REPD
1 September 2021record last updated
East Cambridgeshirecouncil area

REPD also records that the planning permission expired on 19 March 2024, so the project may not go ahead in this form.

Planning timeline

DateStage
7 December 2020Application submitted
19 March 2021Planning permission granted
19 March 2024Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
approved, not built
Record last updated
1 September 2021
Operator or applicant
Lightsource BP
Planning authority
East Cambridgeshire
Planning application reference
20/01654/FUL
Site area
0.6 ha
Address (REPD)
Goose Hall Farm Factory Road, Burwell Cambridge
Council area (by location)
East Cambridgeshire
Time to decision
15 weeks
REPD reference
9528

Who decides

ApplicationsEast CambridgeshireUK
Decided applications (solar, wind, battery)3010,236
Refused1 (3%)19%
Solar refused0 of 2212%
Battery storage refused1 of 816%
Median time from submission to decision15.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Burwell Anchor Lane Farm, Newnham Drovesolar farm50approved, not built0.7
Goosehall Solar Farmsolar farm39.5operational0.8
Anchor Lane, Burwellbattery storage50approved, not built1.6
Burwell Solar Farmsolar farm49.9under construction1.7
Burwellbattery storage50operational1.9
Breach Farm Solar farmsolar farm67operational2.0
Long Barrow Solar Farm Projectsolar farm49.9application submitted2.1
Weirs Drove, Burwellbattery storage30application submitted2.4
Bracks Farmsolar farm28operational2.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2957, 0.3203).