Energy Projects Near You

Renewable energy projects in East Cambridgeshire

37 solar, wind or battery projects of 150 kW or more are located in East Cambridgeshire (REPD, July 2026 extract): 2 pending, 17 approved but not running, 15 operational and 1 refused. The council refused 1 of 30 decided applications (3%; UK 19%), with a median 16 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

37projects in the council area
2awaiting a decision
17approved, not running
3%of decisions refused

How East Cambridgeshire decides

ApplicationsEast CambridgeshireUK
Decided applications (solar, wind, battery)3010,236
Refused1 (3%)19%
Solar refused0 of 2212%
Battery storage refused1 of 816%
Median time from submission to decision15.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Projects in East Cambridgeshire

Projects of 1 MW and more (28)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Wicken Bridleway, Church Roadbattery storagebattery storage400approved, not builtupdated May 2026Mar 2025granted Apr 2026May 2026
Land Southwest of Hightown Drove, Burwellbattery storagebattery storage90refusedupdated May 2026Jul 2025refused Mar 2026May 2026
Breach Farm Solar farmsolar farmsolar farm67operationalupdated Apr 2026Apr 2021granted Dec 2021Apr 2026
Newmarket Road, Bottishambattery storagebattery storage50approved, not builtupdated Feb 2026Nov 2022granted Dec 2023Feb 2026
Burwellbattery storagebattery storage50operationalupdated Mar 2024Dec 2017granted Apr 2018Mar 2024
Anchor Lane, Burwellbattery storagebattery storage50approved, not builtupdated Jun 2025Jul 2024granted May 2025Jun 2025
Burwell Anchor Lane Farm, Newnham Drovesolar farmsolar farm50approved, not builtupdated May 2026Apr 2025granted Mar 2026May 2026
Burwell Solar Farmsolar farmsolar farm49.9under constructionupdated Jan 2022May 2020granted Nov 2020Jan 2022
Reach Roadbattery storagebattery storage49.9approved, not builtupdated Jun 2020May 2020granted Jul 2020Jun 2020
Long Barrow Solar Farm Projectsolar farmsolar farm49.9application submittedupdated Aug 2025Jul 2025—Aug 2025
Newmarket Road, Bottishamsolar farmsolar farm49.9approved, not builtupdated Feb 2026Nov 2022granted Dec 2023Feb 2026
Goosehall Solar Farmsolar farmsolar farm39.5operationalupdated Dec 2021Jul 2015granted Nov 2015Dec 2021
Weirs Drove, Burwellbattery storagebattery storage30application submitted may be out of dateupdated Jul 2021May 2021—Jul 2021
Exningsolar farmsolar farm29.9operationalupdated Feb 2017Oct 2013granted Jul 2014Feb 2017
North Angle Farmsolar farmsolar farm29.4under constructionupdated Dec 2023Aug 2020granted Nov 2020Dec 2023
Bracks Farmsolar farmsolar farm28operationalupdated Oct 2023Apr 2020granted Oct 2021Oct 2023
Stowbridge Farmsolar farmsolar farm24operationalupdated Feb 2015Sep 2012granted Dec 2012Feb 2015
Mingay Farm - extensionsolar farmsolar farm19.3operationalupdated Mar 2015Jul 2013granted Oct 2013Mar 2015
Triangle Solar Farm Parksolar farmsolar farm12operationalupdated Feb 2017Jul 2014granted Oct 2014Feb 2017
Stowbridge Farm - Extension (Phase 2)solar farmsolar farm10operationalupdated May 2015Jul 2014granted Nov 2014May 2015
Stowbridge Farm - Extension (Phase 1)solar farmsolar farm10operationalupdated May 2015Aug 2013granted Mar 2014May 2015
Chittering Solar Farm - extension 2solar farmsolar farm9.6approved, not built may be out of dateupdated May 2019Jun 2014granted Jun 2015May 2019
Berry Fen Wind Farmwind farmwind farm9application withdrawnupdated Jul 2015Jun 2014—Jul 2015
Chittering Solar Farm Extensionsolar farmsolar farm6.3operationalupdated Apr 2013Jul 2012granted Oct 2012Apr 2013
Mingay Farmsolar farmsolar farm5operationalupdated Jul 2011Oct 2010granted Feb 2011Jul 2011
Chittering Solar Farmsolar farmsolar farm5operationalupdated Oct 2012Dec 2010granted Mar 2011Oct 2012
Forest Heath Solar Farmsolar farmsolar farm5operationalupdated Mar 2015Nov 2012granted Jan 2013Mar 2015
Goose Hall Solar Farmsolar farmsolar farm5approved, not built may be out of dateupdated Sep 2021Dec 2020granted Mar 2021Sep 2021
Smaller schemes under 1 MW, mostly rooftop solar (9)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
The Harbour School, Station Road Solar Panels & ASHProoftop solarrooftop solar0.9approved, not built may be out of dateupdated Nov 2022Sep 2022granted Nov 2022Nov 2022
Breach Farm Solar farmbattery storagebattery storage0.7operationalupdated Apr 2026Apr 2021granted Dec 2021Apr 2026
Arthur Rickwood Farm, Chatteris Roadsolar farmsolar farm0.7application withdrawnupdated Sep 2023Apr 2023—Sep 2023
Lees Packhouse, The Gaultrooftop solarrooftop solar0.3approved, not builtupdated Jun 2023Apr 2023granted Jun 2023Jun 2023
Quotient Bioresearch Limited, Newmarket Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Sep 2025granted Nov 2025Jan 2026
Cambridge Commodities, Lancaster Way Business Parkrooftop solarrooftop solar0.2approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024
Mettleham Farm Centre, Hasse Roadrooftop solarrooftop solar0.1approved, not builtupdated Mar 2023Feb 2023granted Mar 2023Mar 2023
Willow Hall Farm, Hillrow Causewayrooftop solarrooftop solar0.1approved, not builtupdated Aug 2025Jul 2025granted Aug 2025Aug 2025
The Cloistersrooftop solarrooftop solar—approved, not builtupdated Jul 2023Apr 2023granted Jun 2023Jul 2023

Postcode districts in East Cambridgeshire

DistrictProjects within 10 kmPendingApprovedOperational
CB615057
CB72721212
CB253661415

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to East Cambridgeshire by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.