Energy Projects Near You

Wicken Bridleway, Church Road (400 MW battery storage)

Wicken Bridleway, Church Road is a 400 MW battery storage project in East Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 8 April 2026, not yet built; the record was last updated on 19 May 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

400 MWbattery storage
approved, not builtstatus in REPD
19 May 2026record last updated
East Cambridgeshirecouncil area

Planning timeline

DateStage
25 March 2025Application submitted
8 April 2026Planning permission granted
8 April 2029Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
400 MW
Status (REPD)
approved, not built
Record last updated
19 May 2026
Operator or applicant
Green Switch Capital Limited
Planning authority
East Cambridgeshire
Planning application reference
25/00303/FUM
Address (REPD)
Field Btw Wicken Bridleway 38 And Soham Bridleway, 126 Church Road, Wicken, Ely
Council area (by location)
East Cambridgeshire
Time to decision
54 weeks
Name in REPD
Wicken Bridleway, Church Road - Battery Energy Storage
REPD reference
16410

Who decides

ApplicationsEast CambridgeshireUK
Decided applications (solar, wind, battery)3010,236
Refused1 (3%)19%
Solar refused0 of 2212%
Battery storage refused1 of 816%
Median time from submission to decision15.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stowbridge Farm - Extension (Phase 2)solar farm10operational7.7
Stowbridge Farm - Extension (Phase 1)solar farm10operational8.0
Stowbridge Farmsolar farm24operational8.4
Triangle Solar Farm Parksolar farm12operational8.7
Mingay Farmsolar farm5operational8.9
North Angle Farmsolar farm29.4under construction9.3
Chittering Solar Farmsolar farm5operational9.5
Chittering Solar Farm - extension 2solar farm9.6approved, not built9.7
Bracks Farmsolar farm28operational9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3995, 0.2623).