Energy Projects Near You

Stowbridge Farm - Extension (Phase 1) (10 MW solar farm)

Stowbridge Farm - Extension (Phase 1) is a 10 MW solar farm project in East Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 March 2015; the record was last updated on 28 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
operationalstatus in REPD
28 May 2015record last updated
East Cambridgeshirecouncil area

Planning timeline

DateStage
20 August 2013Application submitted
6 March 2014Planning permission granted
1 December 2014Construction started
20 March 2015Operational

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
28 May 2015
Operator or applicant
FC Palmer & Sons Ltd
Planning authority
East Cambridgeshire
Planning application reference
S/1516/13/FL
Site area
27.1 ha
Address (REPD)
Stowbridge Farm, Green End, Stretham, Cambridgeshire
Council area (by location)
East Cambridgeshire
Time to decision
28 weeks
REPD reference
2360

Who decides

ApplicationsEast CambridgeshireUK
Decided applications (solar, wind, battery)3010,236
Refused1 (3%)19%
Solar refused0 of 2212%
Battery storage refused1 of 816%
Median time from submission to decision15.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stowbridge Farm - Extension (Phase 2)solar farm10operational0.3
Stowbridge Farmsolar farm24operational0.6
Chittering Solar Farmsolar farm5operational1.5
Chittering Solar Farm - extension 2solar farm9.6approved, not built1.7
Chittering Solar Farm Extensionsolar farm6.3operational1.8
Mingay Farmsolar farm5operational4.3
Mingay Farm - extensionsolar farm19.3operational4.7
North Angle Farmsolar farm29.4under construction6.2
Triangle Solar Farm Parksolar farm12operational6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.331, 0.2258).