Mingay Farm - extension (19.3 MW solar farm)

Mingay Farm - extension is a 19.3 MW solar farm project in East Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 5 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19.3 MWsolar farm
operationalstatus in REPD
5 March 2015record last updated
East Cambridgeshirecouncil area

Planning timeline

DateStage
11 July 2013Application submitted
30 October 2013Planning permission granted
31 March 2014Operational

Project details

Technology
solar farm
Capacity
19.3 MW
Status (REPD)
operational
Record last updated
5 March 2015
Operator or applicant
Octopus Imvetments
Planning authority
East Cambridgeshire
Planning application reference
13/00499/ESF
Site area
35.0 ha
Address (REPD)
Solar Farm, S/O Mingay Farm, Twentypence Road, Wilburton, Ely
Council area (by location)
East Cambridgeshire
Time to decision
16 weeks
REPD reference
1502

Who decides

ApplicationsEast CambridgeshireUK
Decided applications (solar, wind, battery)3010,236
Refused1 (3%)19%
Solar refused0 of 2212%
Battery storage refused1 of 816%
Median time from submission to decision15.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mingay Farmsolar farm5operational1.3
Berry Fen Wind Farmwind farm9application withdrawn3.5
Stowbridge Farmsolar farm24operational4.2
Stowbridge Farm - Extension (Phase 2)solar farm10operational4.7
Chittering Solar Farm Extensionsolar farm6.3operational4.7
Stowbridge Farm - Extension (Phase 1)solar farm10operational4.7
Chittering Solar Farmsolar farm5operational4.7
Chittering Solar Farm - extension 2solar farm9.6approved, not built5.0
Falcon Park, Wilsons Road Solar Farm & Battery Energy Storagesolar farm26application submitted9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3351, 0.1571).