Energy Projects Near You

Chittering Solar Farm - extension 2 (9.6 MW)

Chittering Solar Farm - extension 2 is a 9.6 MW solar farm project in East Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 June 2015, not yet built; the record was last updated on 16 May 2019. REPD also records that the planning permission expired on 16 June 2018, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.6 MWsolar farm
approved, not builtmay be out of datestatus in REPD
16 May 2019record last updated
East Cambridgeshirecouncil area

REPD also records that the planning permission expired on 16 June 2018, so the project may not go ahead in this form.

Planning timeline

DateStage
9 June 2014Application submitted
16 June 2015Planning permission granted
16 June 2018Permission expired

Project details

Technology
solar farm
Capacity
9.6 MW
Status (REPD)
approved, not built
Record last updated
16 May 2019
Operator or applicant
Abbey Renewables (North Fen Solar Energy)
Planning authority
South Cambridgeshire
Planning application reference
S/1331/14/FL
Site area
15.4 ha
Address (REPD)
Land east and south of Radical Farm, Chittering Drove, Chittering, Cambridgeshire, CB25 9PH
Council area (by location)
East Cambridgeshire
Time to decision
53 weeks
REPD reference
1939

Who decides

ApplicationsSouth CambridgeshireUK
Decided applications (solar, wind, battery)4810,236
Refused10 (21%)19%
Solar refused6 of 4012%
Onshore wind refused4 of 545%
Battery storage refused0 of 316%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Chittering Solar Farmsolar farm5operational0.4
Chittering Solar Farm Extensionsolar farm6.3operational0.4
Stowbridge Farmsolar farm24operational1.6
Stowbridge Farm - Extension (Phase 1)solar farm10operational1.7
Stowbridge Farm - Extension (Phase 2)solar farm10operational2.0
Mingay Farm - extensionsolar farm19.3operational5.0
Mingay Farmsolar farm5operational5.1
Anchor Lane, Burwellbattery storage50approved, not built6.1
North Angle Farmsolar farm29.4under construction6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3154, 0.2238).