Chittering Solar Farm (5 MW)

Chittering Solar Farm is a 5 MW solar farm project in East Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 June 2012; the record was last updated on 23 October 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
23 October 2012record last updated
East Cambridgeshirecouncil area

Planning timeline

DateStage
15 December 2010Application submitted
15 March 2011Planning permission granted
28 June 2012Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
23 October 2012
Operator or applicant
Abbey Renewables
Planning authority
South Cambridgeshire
Planning application reference
S/2198/10
Site area
17.8 ha
Address (REPD)
Radical Farm, Chittering Drove, Chittering, Cambridgeshire
Council area (by location)
East Cambridgeshire
Time to decision
13 weeks
REPD reference
1553

Who decides

ApplicationsSouth CambridgeshireUK
Decided applications (solar, wind, battery)4810,236
Refused10 (21%)19%
Solar refused6 of 4012%
Onshore wind refused4 of 545%
Battery storage refused0 of 316%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Chittering Solar Farm - extension 2solar farm9.6approved, not built0.4
Chittering Solar Farm Extensionsolar farm6.3operational0.4
Stowbridge Farmsolar farm24operational1.2
Stowbridge Farm - Extension (Phase 1)solar farm10operational1.5
Stowbridge Farm - Extension (Phase 2)solar farm10operational1.7
Mingay Farm - extensionsolar farm19.3operational4.7
Mingay Farmsolar farm5operational4.8
Anchor Lane, Burwellbattery storage50approved, not built6.4
North Angle Farmsolar farm29.4under construction6.5