Berry Fen Wind Farm (9 MW)

Berry Fen Wind Farm is a 9 MW wind farm project in East Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 26 June 2015; the record was last updated on 1 July 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9 MWwind farm
application withdrawnstatus in REPD
1 July 2015record last updated
East Cambridgeshirecouncil area

Planning timeline

DateStage
30 June 2014Application submitted
26 June 2015Application withdrawn

Project details

Technology
wind farm
Capacity
9 MW
Status (REPD)
application withdrawn
Record last updated
1 July 2015
Operator or applicant
REG Windpower
Planning authority
East Cambridgeshire
Planning application reference
14/00728/ESF
Turbines
3
Address (REPD)
Berry Fen, Aldreth, Ely, Cambridgeshire
Council area (by location)
East Cambridgeshire
REPD reference
4341

Who decides

ApplicationsEast CambridgeshireUK
Decided applications (solar, wind, battery)3010,236
Refused1 (3%)19%
Solar refused0 of 2212%
Battery storage refused1 of 816%
Median time from submission to decision15.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mingay Farm - extensionsolar farm19.3operational3.5
Mingay Farmsolar farm5operational3.8
Stowbridge Farmsolar farm24operational7.6
Stowbridge Farm - Extension (Phase 2)solar farm10operational8.0
Stowbridge Farm - Extension (Phase 1)solar farm10operational8.1
Chittering Solar Farm Extensionsolar farm6.3operational8.2
Chittering Solar Farmsolar farm5operational8.2
Chittering Solar Farm - extension 2solar farm9.6approved, not built8.5
Falcon Park, Wilsons Road Solar Farm & Battery Energy Storagesolar farm26application submitted9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3492, 0.1109).