Energy Projects Near You

Bracks Farm (28 MW solar farm)

Bracks Farm is a 28 MW solar farm project in East Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 4 October 2023; the record was last updated on 4 October 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

28 MWsolar farm
operationalstatus in REPD
4 October 2023record last updated
East Cambridgeshirecouncil area

Planning timeline

DateStage
21 April 2020Application submitted
12 October 2021Planning permission granted
4 October 2023Operational

Project details

Technology
solar farm
Capacity
28 MW
Status (REPD)
operational
Record last updated
4 October 2023
Operator or applicant
British Solar Renewables / BayWa r.e. UK Limited
Planning authority
East Cambridgeshire
Planning application reference
20/00522/FUM
Site area
48.1 ha
Address (REPD)
Bracks Farm, Wicken, Ely,
Council area (by location)
East Cambridgeshire
Time to decision
77 weeks
Contracts for Difference
AR4
REPD reference
7363

Who decides

ApplicationsEast CambridgeshireUK
Decided applications (solar, wind, battery)3010,236
Refused1 (3%)19%
Solar refused0 of 2212%
Battery storage refused1 of 816%
Median time from submission to decision15.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
North Angle Farmsolar farm29.4under construction0.5
Triangle Solar Farm Parksolar farm12operational1.1
Goose Hall Solar Farmsolar farm5approved, not built2.6
Burwell Anchor Lane Farm, Newnham Drovesolar farm50approved, not built2.9
Goosehall Solar Farmsolar farm39.5operational2.9
Breach Farm Solar farmsolar farm67operational3.6
Anchor Lane, Burwellbattery storage50approved, not built3.7
Burwell Solar Farmsolar farm49.9under construction4.0
Burwellbattery storage50operational4.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.319, 0.319).