Energy Projects Near You

Breach Farm Solar farm (67 MW)

Breach Farm Solar farm is a 67 MW solar farm project in East Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2023; the record was last updated on 17 April 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

67 MWsolar farm
operationalstatus in REPD
17 April 2026record last updated
East Cambridgeshirecouncil area

Planning timeline

DateStage
29 April 2021Application submitted
10 December 2021Planning permission granted
1 December 2023Operational

Project details

Technology
solar farm
Capacity
67 MW
Status (REPD)
operational
Record last updated
17 April 2026
Operator or applicant
Octopus Renewables Infrastructure Trust
Planning authority
East Cambridgeshire
Planning application reference
DC/21/0968/FUL
Site area
73.0 ha
Address (REPD)
Land South Of Breach Farm Ness Road Burwell Cambridge
Council area (by location)
East Cambridgeshire
Time to decision
32 weeks
Name in REPD
Breach Farm - Solar farm
REPD reference
8479

The scheme also includes 0.7 MW of battery storage, recorded separately in REPD (operational).

Who decides

ApplicationsEast CambridgeshireUK
Decided applications (solar, wind, battery)3010,236
Refused1 (3%)19%
Solar refused0 of 2212%
Battery storage refused1 of 816%
Median time from submission to decision15.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Goose Hall Solar Farmsolar farm5approved, not built2.0
Long Barrow Solar Farm Projectsolar farm49.9application submitted2.0
Land Southwest of Hightown Drove, Burwellbattery storage90refused2.6
Burwell Anchor Lane Farm, Newnham Drovesolar farm50approved, not built2.6
Burwellbattery storage50operational2.7
Goosehall Solar Farmsolar farm39.5operational2.7
Weirs Drove, Burwellbattery storage30application submitted3.1
Forest Heath Solar Farmsolar farm5operational3.2
Burwell Solar Farmsolar farm49.9under construction3.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2919, 0.3492).