Land Southwest of Hightown Drove, Burwell (90 MW battery storage)

Land Southwest of Hightown Drove, Burwell is a 90 MW battery storage project in East Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 9 March 2026; the record was last updated on 1 May 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

90 MWbattery storage
refusedstatus in REPD
1 May 2026record last updated
East Cambridgeshirecouncil area

Planning timeline

DateStage
10 July 2025Application submitted
9 March 2026Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
90 MW
Status (REPD)
refused
Record last updated
1 May 2026
Operator or applicant
Grenergy Renewables UK Limited
Planning authority
East Cambridgeshire
Planning application reference
25/00639/FUM
Address (REPD)
Sw/O Hightown Drove, Burwell, Cambridge
Council area (by location)
East Cambridgeshire
Time to decision
35 weeks
Name in REPD
Land Southwest of Hightown Drove, Burwell - Battery Energy Storage System
REPD reference
17433

Who decides

ApplicationsEast CambridgeshireUK
Decided applications (solar, wind, battery)3010,236
Refused1 (3%)19%
Solar refused0 of 2212%
Battery storage refused1 of 816%
Median time from submission to decision15.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Long Barrow Solar Farm Projectsolar farm49.9application submitted0.6
Reach Roadbattery storage49.9approved, not built0.7
Weirs Drove, Burwellbattery storage30application submitted0.9
Burwellbattery storage50operational1.0
Burwell Solar Farmsolar farm49.9under construction2.0
Anchor Lane, Burwellbattery storage50approved, not built2.5
Goosehall Solar Farmsolar farm39.5operational2.6
Burwell Anchor Lane Farm, Newnham Drovesolar farm50approved, not built2.6
Breach Farm Solar farmsolar farm67operational2.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2727, 0.3274).