Energy Projects Near You

Newmarket Road, Bottisham (49.9 MW solar farm)

Newmarket Road, Bottisham is a 49.9 MW solar farm project in East Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 December 2023, not yet built; the record was last updated on 20 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
20 February 2026record last updated
East Cambridgeshirecouncil area

Planning timeline

DateStage
18 November 2022Application submitted
21 December 2023Planning permission granted
21 December 2026Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
20 February 2026
Operator or applicant
Ridge Clean Energy Limited
Planning authority
East Cambridgeshire
Planning application reference
22/01291/ESF
Site area
76.3 ha
Address (REPD)
Six Oaks Renewable Energy Park Newmarket Road Bottisham
Council area (by location)
East Cambridgeshire
Time to decision
57 weeks
Contracts for Difference
AR7a
Name in REPD
Newmarket Road, Bottisham - Solar Array
REPD reference
10485

The scheme also includes 50 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsEast CambridgeshireUK
Decided applications (solar, wind, battery)3010,236
Refused1 (3%)19%
Solar refused0 of 2212%
Battery storage refused1 of 816%
Median time from submission to decision15.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Great Wilbraham Solar Farmsolar farm38.1operational3.6
Exningsolar farm29.9operational5.9
Wadlow Wind Farmwind farm26operational6.0
Reach Roadbattery storage49.9approved, not built6.4
Weirs Drove, Burwellbattery storage30application submitted6.8
Land Southwest of Hightown Drove, Burwellbattery storage90refused7.0
Low Fen, Drove Way Solar Farmsolar farm50application submitted7.3
Burwellbattery storage50operational7.3
Long Barrow Solar Farm Projectsolar farm49.9application submitted7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2161, 0.2829).