Abbey Farm (5 MW solar farm)

Abbey Farm is a 5 MW solar farm project in South Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 1 April 2016; the record was last updated on 4 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
application withdrawnstatus in REPD
4 May 2016record last updated
South Cambridgeshirecouncil area

Planning timeline

DateStage
15 October 2015Application submitted
1 April 2016Application withdrawn

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
application withdrawn
Record last updated
4 May 2016
Operator or applicant
Push Energy
Planning authority
South Cambridgeshire
Planning application reference
S/2617/15/FL
Site area
8.6 ha
Address (REPD)
Land at Abbey Farm, Grange Road, Ickleton, Saffron Walden, Essex, East of England
Council area (by location)
South Cambridgeshire
REPD reference
5877

Who decides

ApplicationsSouth CambridgeshireUK
Decided applications (solar, wind, battery)4810,236
Refused10 (21%)19%
Solar refused6 of 4012%
Onshore wind refused4 of 545%
Battery storage refused0 of 316%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Rectory Farmsolar farm5application withdrawn0.3
Manor Farmsolar farm14refused4.2
Black Peak Farmsolar farm31.8operational6.9
Sawston Solar Farm (Land North of Dales Manor Business Park)solar farm14refused on appeal7.3
Little Linton Farmwind farm16refused on appeal8.8
Butlers Farmsolar farm7.7refused on appeal9.2
Munceys Farmsolar farm31.6operational9.5
River Mel Solar Farm & Battery Storage Systemsolar farm25application submitted9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0731, 0.1494).