Energy Projects Near You

Ginns Road, Stocking Pelham (400 MW battery storage)

Ginns Road, Stocking Pelham is a 400 MW battery storage project in East Hertfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 29 April 2025, not yet built; the record was last updated on 25 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

400 MWbattery storage
approved, not builtstatus in REPD
25 July 2025record last updated
East Hertfordshirecouncil area

Planning timeline

DateStage
4 November 2024Application submitted
29 April 2025Planning permission granted
29 April 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
400 MW
Status (REPD)
approved, not built
Record last updated
25 July 2025
Operator or applicant
FRV TH Powertek Limited
Planning authority
East Hertfordshire
Planning application reference
3/24/1953/FUL
Address (REPD)
Ginns Road Stocking Pelham
Council area (by location)
East Hertfordshire
Time to decision
25 weeks
Name in REPD
Ginns Road, Stocking Pelham - Battery Energy Storage
REPD reference
16769

Who decides

ApplicationsEast HertfordshireUK
Decided applications (solar, wind, battery)2010,236
Refused7 (35%)19%
Solar refused4 of 1312%
Onshore wind refused2 of 245%
Battery storage refused1 of 516%
Median time from submission to decision22.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dellows, Ginns Roadbattery storage90application submitted0.7
Stocking Pelhambattery storage50refused0.8
Greens Farmbattery storage50approved, not built0.9
Pelhambattery storage49operational0.9
Berden Hall Solar Farmsolar farm56approved, not built1.7
Maggots End Road, Berden Solar Farm & Battery Storagesolar farm49.9refused3.2
Wickham Hall Estate Solar Photovoltaic Farmsolar farm35approved, not built5.3
Wickham Hall Estate Solar Photovoltaic Farmsolar farm20approved, not built5.8
Wickham Hall Estatebattery storage10approved, not built5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9384, 0.1057).