Water Hall Farm, Waterhall Road Solar Farm (35 MW)

Water Hall Farm, Waterhall Road Solar Farm is a 35 MW solar farm project in West Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 July 2025, not yet built; the record was last updated on 27 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35 MWsolar farm
approved, not builtstatus in REPD
27 February 2026record last updated
West Suffolkcouncil area

Planning timeline

DateStage
19 July 2023Application submitted
4 July 2025Planning permission granted
4 July 2030Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
35 MW
Status (REPD)
approved, not built
Record last updated
27 February 2026
Operator or applicant
Bluefield Renewable Developments Limited
Planning authority
West Suffolk
Planning application reference
DC/23/1127/FUL
Site area
41.6 ha
Address (REPD)
Solar Farm Water Hall Farm ,Waterhall Road ,Wixoe
Council area (by location)
West Suffolk
Time to decision
102 weeks
Contracts for Difference
AR7a
Name in REPD
Water Hall Farm, Waterhall Road - Solar Farm
REPD reference
13120

Earlier applications for this site

ApplicationMWSubmittedOutcome
Totmonslow Farm Solar Photovoltaic Farm SMD/2022/03431527 July 2022refused 28 February 2023

Who decides

ApplicationsWest SuffolkUK
Decided applications (solar, wind, battery)3810,236
Refused5 (13%)19%
Solar refused4 of 3312%
Battery storage refused1 of 516%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Surmer Hall, Church Walk Solar Farm & Battery Storagesolar farm36approved, not built2.6
Broxted Solar Farm (Stradishall Airfield)solar farm31.6operational7.4
Cutbush Farm, Belchamp St Paulsolar farm50under construction7.7
Claredown Farmbattery storage20operational7.9
Big Deere Lodgesolar6refused8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0665, 0.493).