Claredown Farm (20 MW battery storage)

Claredown Farm is a 20 MW battery storage project in Braintree, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 27 February 2018; the record was last updated on 26 November 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
operationalstatus in REPD
26 November 2019record last updated
Braintreecouncil area

Planning timeline

DateStage
4 April 2017Application submitted
2 August 2017Planning permission granted
1 September 2017Construction started
27 February 2018Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
operational
Record last updated
26 November 2019
Operator or applicant
Zenobe (formerly Energy Reservoir 15)
Planning authority
Braintree
Planning application reference
17/00583/FUL
Address (REPD)
Land at Claredown Farm, Hickford Hill, Belchamp St Paul
Council area (by location)
Braintree
Time to decision
17 weeks
REPD reference
6945

Who decides

ApplicationsBraintreeUK
Decided applications (solar, wind, battery)3410,236
Refused3 (9%)19%
Solar refused3 of 2512%
Battery storage refused0 of 916%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cutbush Farm, Belchamp St Paulsolar farm50under construction2.1
Big Deere Lodgesolar6refused2.3
Pentlow Hillsolar farm24operational3.8
Wales End Road, Cavendishbattery storage10application submitted4.6
Wales End Road, Cavendish Solar Farmsolar farm12.5application submitted4.6
Water Hall Farm, Waterhall Road Solar Farmsolar farm35approved, not built7.9
Broxted Solar Farm (Stradishall Airfield)solar farm31.6operational9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0707, 0.6078).