Pentlow Hill (24 MW solar farm)
Pentlow Hill is a 24 MW solar farm project in Braintree, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 10 June 2024; the record was last updated on 1 July 2024.
24 MWsolar farm
operationalstatus in REPD
1 July 2024record last updated
Braintreecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 10 July 2020 | Application submitted |
| 23 April 2021 | Planning permission granted |
| 10 June 2024 | Operational |
Project details
- Technology
- solar farm
- Capacity
- 24 MW
- Status (REPD)
- operational
- Record last updated
- 1 July 2024
- Operator or applicant
- Nextpower SPV 11 Limited
- Planning authority
- Braintree
- Planning application reference
- 20/01107/FUL
- Site area
- 28.4 ha
- Address (REPD)
- Land East Of, Pentlow Street, Pentlow, Sudbury, Suffolk
- Council area (by location)
- Braintree
- Time to decision
- 41 weeks
- Contracts for Difference
- AR4
- REPD reference
- 7666
Who decides
| Applications | Braintree | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 34 | 10,236 |
| Refused | 3 (9%) | 19% |
| Solar refused | 3 of 25 | 12% |
| Battery storage refused | 0 of 9 | 16% |
| Median time from submission to decision | 15.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 2 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Claredown Farm | battery storage | 20 | operational | 3.8 |
| Wales End Road, Cavendish | battery storage | 10 | application submitted | 4.6 |
| Wales End Road, Cavendish Solar Farm | solar farm | 12.5 | application submitted | 4.6 |
| Big Deere Lodge | solar | 6 | refused | 4.7 |
| Cutbush Farm, Belchamp St Paul | solar farm | 50 | under construction | 5.0 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0782, 0.6628).