Pentlow Hill (24 MW solar farm)

Pentlow Hill is a 24 MW solar farm project in Braintree, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 10 June 2024; the record was last updated on 1 July 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24 MWsolar farm
operationalstatus in REPD
1 July 2024record last updated
Braintreecouncil area

Planning timeline

DateStage
10 July 2020Application submitted
23 April 2021Planning permission granted
10 June 2024Operational

Project details

Technology
solar farm
Capacity
24 MW
Status (REPD)
operational
Record last updated
1 July 2024
Operator or applicant
Nextpower SPV 11 Limited
Planning authority
Braintree
Planning application reference
20/01107/FUL
Site area
28.4 ha
Address (REPD)
Land East Of, Pentlow Street, Pentlow, Sudbury, Suffolk
Council area (by location)
Braintree
Time to decision
41 weeks
Contracts for Difference
AR4
REPD reference
7666

Who decides

ApplicationsBraintreeUK
Decided applications (solar, wind, battery)3410,236
Refused3 (9%)19%
Solar refused3 of 2512%
Battery storage refused0 of 916%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Claredown Farmbattery storage20operational3.8
Wales End Road, Cavendishbattery storage10application submitted4.6
Wales End Road, Cavendish Solar Farmsolar farm12.5application submitted4.6
Big Deere Lodgesolar6refused4.7
Cutbush Farm, Belchamp St Paulsolar farm50under construction5.0