Sunnica Energy Farm (East and West) (500 MW solar farm)

Sunnica Energy Farm (East and West) is a 500 MW solar farm project in West Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 12 July 2024, not yet built; the record was last updated on 16 December 2024. As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010106).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

500 MWsolar farm
approved, not builtstatus in REPD
16 December 2024record last updated
West Suffolkcouncil area

Planning timeline

DateStage
18 November 2021Application submitted
12 July 2024Development consent granted (Secretary of State)

Project details

Technology
solar farm
Capacity
500 MW
Status (REPD)
approved, not built
Record last updated
16 December 2024
Operator or applicant
Sunnica
Planning authority
The Planning Inspectorate - National Infrastructure
Planning application reference
EN010106
Site area
621.6 ha
Address (REPD)
Land 4.5km East of Burwell and Land 2.5km South-West of Mildenhall
Council area (by location)
West Suffolk
Time to decision
138 weeks
REPD reference
7188

The scheme also includes 8.8 MW of battery storage, recorded separately in REPD (approved, not built).

Official project record at the Planning Inspectorate (EN010106)

Who decides

As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010106). All Energy Secretary decisions on solar and wind farms. The Planning Inspectorate - National Infrastructure refused 7% of 46 decided solar, wind and battery applications in REPD (median 73 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Bay Farmsolar farm8.1operational1.4
Icklingham Solar Farmsolar farm8permission expired6.6
Forest Heath Solar Farmsolar farm5operational8.0
Lackford Estate Solar Parksolar farm20.9operational9.6
Breach Farm Solar farmsolar farm67operational9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3247, 0.4829).