Lackford Estate Solar Park (20.9 MW)

Lackford Estate Solar Park is a 20.9 MW solar farm project in West Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 30 April 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20.9 MWsolar farm
operationalstatus in REPD
30 April 2014record last updated
West Suffolkcouncil area

Planning timeline

DateStage
13 August 2013Application submitted
2 November 2013Planning permission granted
31 March 2014Operational

Project details

Technology
solar farm
Capacity
20.9 MW
Status (REPD)
operational
Record last updated
30 April 2014
Operator or applicant
Lackford Estate Solar Park Ltd
Planning authority
West Suffolk
Planning application reference
DC/13/0017/FUL
Address (REPD)
Bury St Edmunds, Suffolk IP28
Council area (by location)
West Suffolk
Time to decision
12 weeks
REPD reference
1338

Who decides

ApplicationsWest SuffolkUK
Decided applications (solar, wind, battery)3810,236
Refused5 (13%)19%
Solar refused4 of 3312%
Battery storage refused1 of 516%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Icklingham Solar Farmsolar farm8permission expired6.4
Ingham North Solarsolar farm14.2operational7.6
Bay Farmsolar farm8.1operational8.2
Solar Farm at Poulters Lanesolar farm40refused9.3
Sunnica Energy Farm (East and West)solar farm500approved, not built9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2888, 0.611).