Ingham North Solar (14.2 MW)

Ingham North Solar is a 14.2 MW solar farm project in West Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 March 2021; the record was last updated on 16 January 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14.2 MWsolar farm
operationalstatus in REPD
16 January 2026record last updated
West Suffolkcouncil area

Planning timeline

DateStage
26 September 2016Application submitted
24 March 2017Planning permission granted
23 March 2021Operational

Project details

Technology
solar farm
Capacity
14.2 MW
Status (REPD)
operational
Record last updated
16 January 2026
Operator or applicant
Solafields/Ingham Renewables
Planning authority
West Suffolk
Planning application reference
DC/16/2140/FUL
Address (REPD)
Land north west of Ingham, The Street, Ingham, Bury St. Edmunds
Council area (by location)
West Suffolk
Time to decision
26 weeks
REPD reference
6248

Earlier applications for this site

ApplicationMWSubmittedOutcome
Ingham solar farm SE/13/0905/FUL2624 July 2013refused 7 February 2014

Who decides

ApplicationsWest SuffolkUK
Decided applications (solar, wind, battery)3810,236
Refused5 (13%)19%
Solar refused4 of 3312%
Battery storage refused1 of 516%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
West Farm (Barnham)solar farm29refused on appeal4.7
Honington Solar Farmsolar farm13.6operational5.8
Lackford Estate Solar Parksolar farm20.9operational7.6
Icklingham Solar Farmsolar farm8permission expired9.5
Firsfield Solar Farmsolar farm46.9approved, not built9.9
Bardwell Fields, Knox Lane Solar Farmsolar farm42application submitted9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.319, 0.7109).