Honington Solar Farm (13.6 MW)

Honington Solar Farm is a 13.6 MW solar farm project in West Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 31 August 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.6 MWsolar farm
operationalstatus in REPD
31 August 2017record last updated
West Suffolkcouncil area

Planning timeline

DateStage
22 August 2012Application submitted
10 December 2012Planning permission granted
31 March 2014Operational

Project details

Technology
solar farm
Capacity
13.6 MW
Status (REPD)
operational
Record last updated
31 August 2017
Operator or applicant
NextEnergy Solar Fund (NESF)
Planning authority
West Suffolk
Planning application reference
SE/12/1069/FUL
Site area
22.6 ha
Address (REPD)
Land at Euston Estate, Honnington, Suffolk
Council area (by location)
West Suffolk
Time to decision
16 weeks
REPD reference
1757

Who decides

ApplicationsWest SuffolkUK
Decided applications (solar, wind, battery)3810,236
Refused5 (13%)19%
Solar refused4 of 3312%
Battery storage refused1 of 516%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Firsfield Solar Farmsolar farm46.9approved, not built4.1
Bardwell Fields, Knox Lane Solar Farmsolar farm42application submitted5.0
Ingham North Solarsolar farm14.2operational5.8
West Farm (Barnham)solar farm29refused on appeal6.2
Woodlands Farmsolar farm49.9approved, not built8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3396, 0.7886).