Energy Projects Near You

West Farm (Barnham) (29 MW solar farm)

West Farm (Barnham) is a 29 MW solar farm project in West Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 6 January 2016; the record was last updated on 5 February 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29 MWsolar farm
refused on appealstatus in REPD
5 February 2016record last updated
West Suffolkcouncil area

Planning timeline

DateStage
3 December 2013Application submitted
4 December 2014Refused by the planning authority
2 February 2015Appeal lodged
6 January 2016Appeal refused

Project details

Technology
solar farm
Capacity
29 MW
Status (REPD)
refused on appeal
Record last updated
5 February 2016
Operator or applicant
Elveden Farms Ltd
Planning authority
West Suffolk
Planning application reference
DC/13/0801/FUL
Appeal reference
APP/E3525/W/14/3001409
Site area
66.8 ha
Address (REPD)
Land West Of West Farm Dukes Ride Barnham Suffolk
Council area (by location)
West Suffolk
Time to decision
52 weeks
REPD reference
2087

Who decides

ApplicationsWest SuffolkUK
Decided applications (solar, wind, battery)3810,236
Refused5 (13%)19%
Solar refused4 of 3312%
Battery storage refused1 of 516%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ingham North Solarsolar farm14.2operational4.7
Honington Solar Farmsolar farm13.6operational6.2
Woodlands Farmsolar farm49.9approved, not built6.6
Icklingham Solar Farmsolar farm8permission expired9.0
Firsfield Solar Farmsolar farm46.9approved, not built9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3611, 0.7048).