Icklingham Solar Farm (8 MW)

Icklingham Solar Farm is an 8 MW solar farm project in West Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 7 August 2017; the record was last updated on 21 November 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWsolar farm
permission expiredstatus in REPD
21 November 2019record last updated
West Suffolkcouncil area

Planning timeline

DateStage
16 May 2013Application submitted
7 August 2013Planning permission granted
7 August 2017Permission expired

Project details

Technology
solar farm
Capacity
8 MW
Status (REPD)
permission expired
Record last updated
21 November 2019
Operator or applicant
Elveden Farms Ltd
Planning authority
West Suffolk
Planning application reference
F/2013/0258/ESF
Site area
17.1 ha
Address (REPD)
Land west of Avenue Farm Lakenheath Road (B1112) Icklingham
Council area (by location)
West Suffolk
Time to decision
12 weeks
REPD reference
1822

Who decides

ApplicationsWest SuffolkUK
Decided applications (solar, wind, battery)3810,236
Refused5 (13%)19%
Solar refused4 of 3312%
Battery storage refused1 of 516%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bay Farmsolar farm8.1operational6.0
Lackford Estate Solar Parksolar farm20.9operational6.4
Sunnica Energy Farm (East and West)solar farm500approved, not built6.6
West Farm (Barnham)solar farm29refused on appeal9.0
Ingham North Solarsolar farm14.2operational9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3425, 0.5759).