Energy Projects Near You

Hall Farm, West End Northwold Solar Farm (10 MW)

Hall Farm, West End Northwold Solar Farm is a 10 MW solar farm project in King's Lynn and West Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 February 2025; the record was last updated on 24 March 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
operationalstatus in REPD
24 March 2025record last updated
King's Lynn and West Norfolkcouncil area

Planning timeline

DateStage
10 December 2021Application submitted
15 March 2022Planning permission granted
28 February 2025Operational

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
24 March 2025
Operator or applicant
Ampyr Solar Europe
Planning authority
King's Lynn and West Norfolk
Planning application reference
21/02302/FM
Site area
18.4 ha
Address (REPD)
90 West End Northwold, Thetford
Council area (by location)
King's Lynn and West Norfolk
Time to decision
14 weeks
Name in REPD
Hall Farm, West End Northwold - Solar Farm
REPD reference
18382

The scheme also includes 7.5 MW of battery storage, recorded separately in REPD (operational).

Who decides

ApplicationsKing's Lynn and West NorfolkUK
Decided applications (solar, wind, battery)6010,236
Refused11 (18%)19%
Solar refused5 of 3812%
Onshore wind refused3 of 645%
Battery storage refused3 of 1616%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Reaches Farm Solar Parksolar farm6.1operational1.7
Solar PV Panelssolar farm15approved, not built2.0
Meadow Farm solar parksolar farm6operational2.3
Land North Of, Whittington Hilsolar farm5abandoned2.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5459, 0.577).