Toggam Farm (12.5 MW solar farm)

Toggam Farm is a 12.5 MW solar farm project in West Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 March 2016; the record was last updated on 24 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12.5 MWsolar farm
operationalstatus in REPD
24 August 2016record last updated
West Suffolkcouncil area

Planning timeline

DateStage
13 December 2012Application submitted
10 May 2013Planning permission granted
6 February 2016Construction started
24 March 2016Operational

Project details

Technology
solar farm
Capacity
12.5 MW
Status (REPD)
operational
Record last updated
24 August 2016
Operator or applicant
Forest Heath District Council
Planning authority
West Suffolk
Planning application reference
F/2012/0741/FUL
Site area
17.6 ha
Address (REPD)
Newfen Gravel Drove, Lakenheath, Brandon, Suffolk, IP27 9LN
Council area (by location)
West Suffolk
Time to decision
21 weeks
REPD reference
2076

Who decides

ApplicationsWest SuffolkUK
Decided applications (solar, wind, battery)3810,236
Refused5 (13%)19%
Solar refused4 of 3312%
Battery storage refused1 of 516%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Brandon Fields Estate, Brandon Fieldssolar farm28application submitted5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4334, 0.5009).