Energy Projects Near You

Solar, wind and battery projects near King's Lynn (PE33)

5 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PE33 (King's Lynn and West Norfolk): 2 approved but not yet running, 2 operational. The largest live scheme is Sluice Road, Wiggenhall St Germans Solar Array & Battery Storage ( MW solar farm, approved on 8 October 2025, not yet built), 9.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5projects within 10 km
0awaiting a decision
2approved, not running
2operational

Projects within 10 km of PE33

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Field north of Water Treatment Works / Hoggs Drovesolar farmsolar farm1operationalupdated Oct 2022Oct 2018granted May 2021Oct 2022King's Lynn and West Norfolk5.5
Ryston Estate Solar Parksolar farmsolar farm4.8operationalupdated Aug 2015May 2013granted Aug 2013Aug 2015King's Lynn and West Norfolk7.4
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Alfred G Pearce, Castle Road Solar Farmsolar farmsolar farm0.7refusedupdated Apr 2024Nov 2022refused Mar 2024Apr 2024King's Lynn and West Norfolk3.6
Sluice Road, Wiggenhall St Germans Solar Array & Battery Storagesolar farmsolar farm—approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025King's Lynn and West Norfolk9.8
Sluice Road, Wiggenhall St Germans Solar Array & Battery Storagebattery storagebattery storage—approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025King's Lynn and West Norfolk9.8

Distance from the average position of the PE33 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm401210
Battery storage101000

MW in pipeline: pending, approved and under-construction capacity.

How King's Lynn and West Norfolk decides solar, wind and battery applications

ApplicationsKing's Lynn and West NorfolkUK
Decided applications (solar, wind, battery)6010,236
Refused11 (18%)19%
Solar refused5 of 3812%
Onshore wind refused3 of 645%
Battery storage refused3 of 1616%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

All projects in King's Lynn and West Norfolk

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.