Energy Projects Near You

Solar, wind and battery projects near Dereham (NR19)

9 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NR19 (Breckland): 3 are waiting for a planning decision, 4 approved but not yet running, 1 operational. The largest live scheme is The Park Farm, Birds Corner (800 MW battery storage, application submitted on 23 June 2025, no decision recorded), 4.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9projects within 10 km
3awaiting a decision
4approved, not running
1operational

Projects within 10 km of NR19

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Park Farm, Birds Cornerbattery storagebattery storage800application submittedupdated Aug 2025Jun 2025—Aug 2025Breckland4.8
The Park Farm, Birds Cornersolar farmsolar farm49.9application submittedupdated Aug 2025Nov 2024—Aug 2025Breckland4.8
Shipdham Wind Parkwind farmwind farm4.6refusedupdated Nov 2015Aug 2011refused Sep 2012Nov 2015Breckland5.1
Huntingfield Solar Farmsolar farmsolar farm4.4operationalupdated Sep 2018Jun 2015granted Sep 2015Sep 2018Breckland6.6
Dykewood Farm, Water End Lanesolar farmsolar farm49.9application submittedupdated Aug 2025Jul 2025—Aug 2025Breckland6.9
Three Bridges Solar Farmsolar farmsolar farm15approved, not builtupdated Feb 2026Oct 2020granted Mar 2021Feb 2026Breckland9.2
Three Bridges Solar Farmbattery storagebattery storage15approved, not builtupdated Feb 2026Oct 2020granted Mar 2021Feb 2026Breckland9.2
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Dereham Leisure Centre, Station Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024Breckland1.3
Station Roadrooftop solarrooftop solar0.3approved, not builtupdated Mar 2022Feb 2022granted Apr 2022Mar 2022Breckland1.3

Distance from the average position of the NR19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm42110115
Rooftop solar202000.5
Wind farm100010
Battery storage21100815

MW in pipeline: pending, approved and under-construction capacity.

How Breckland decides solar, wind and battery applications

ApplicationsBrecklandUK
Decided applications (solar, wind, battery)3810,236
Refused7 (18%)19%
Solar refused4 of 2812%
Onshore wind refused3 of 745%
Battery storage refused0 of 316%
Median time from submission to decision19.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

All projects in Breckland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.