Energy Projects Near You

Three Bridges Solar Farm (15 MW)

Three Bridges Solar Farm is a 15 MW solar farm project in Breckland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 10 March 2021, not yet built; the record was last updated on 20 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWsolar farm
approved, not builtstatus in REPD
20 February 2026record last updated
Brecklandcouncil area

Planning timeline

DateStage
12 October 2020Application submitted
10 March 2021Planning permission granted

Project details

Technology
solar farm
Capacity
15 MW
Status (REPD)
approved, not built
Record last updated
20 February 2026
Operator or applicant
Pathfinder Clean Energy UK Dev Limited
Planning authority
Breckland
Planning application reference
3PL/2020/1134/F
Site area
35.2 ha
Address (REPD)
Three Bridges Solar Farm
Council area (by location)
Breckland
Time to decision
21 weeks
Contracts for Difference
AR7a
REPD reference
8219

The scheme also includes 15 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsBrecklandUK
Decided applications (solar, wind, battery)3810,236
Refused7 (18%)19%
Solar refused4 of 2812%
Onshore wind refused3 of 745%
Battery storage refused0 of 316%
Median time from submission to decision19.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Woodforde Farmsolar farm9operational3.3
The Old Airfieldsolar farm5operational4.5
Nowhere Lane, Norwichsolar farm40approved, not built5.0
Hall Road, Alderfordsolar farm28refused6.0
Colton Solar photovoltaic farm, Battery storagebattery storage30under construction8.0
Colton Solar photovoltaic farm, Battery storagesolar farm30under construction8.0
Guestwickwind farm12refused9.7
Warren Wood Energy Park Solar Farm & Battery Energy Storagesolar farm25refused10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7148, 1.0489).