Energy Projects Near You

Dykewood Farm, Water End Lane (49.9 MW solar farm)

Dykewood Farm, Water End Lane is a 49.9 MW solar farm project in Breckland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 10 July 2025, no decision recorded; the record was last updated on 15 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
application submittedstatus in REPD
15 August 2025record last updated
Brecklandcouncil area

Planning timeline

DateStage
10 July 2025Application submitted

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
15 August 2025
Operator or applicant
Regener8 Power Limited
Planning authority
Breckland
Planning application reference
PL/2025/0998/FMAJ
Site area
95.5 ha
Address (REPD)
Dykewood Farm, Water End Lane, Beeston, Kings Lynn
Council area (by location)
Breckland
Name in REPD
Dykewood Farm, Water End Lane - Solar Panels
REPD reference
18422

Who decides

ApplicationsBrecklandUK
Decided applications (solar, wind, battery)3810,236
Refused7 (18%)19%
Solar refused4 of 2812%
Onshore wind refused3 of 745%
Battery storage refused0 of 316%
Median time from submission to decision19.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Jafa, Great Dunham Solar Photovoltaic Farm & Battery Storagesolar farm49.9approved, not built5.2
Claypit Moor Solar Farm (Lexham)solar farm7.9operational6.2
Shereford Road, West Raynham Estatebattery storage50approved, not built9.1
The Park Farm, Birds Cornersolar farm49.9application submitted9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7049, 0.8397).