Energy Projects Near You

Solar, wind and battery projects near Thetford (IP25)

12 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IP25 (Breckland): 2 are waiting for a planning decision, 4 approved but not yet running, 5 operational. The largest live scheme is The Park Farm, Birds Corner (800 MW battery storage, application submitted on 23 June 2025, no decision recorded), 7.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12projects within 10 km
2awaiting a decision
4approved, not running
5operational

Projects within 10 km of IP25

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Little Cressingham, Cranswick Country Foodssolar farmsolar farm1.8approved, not built may be out of dateupdated Apr 2023Dec 2022granted Mar 2023Apr 2023Breckland3.0
Huntingfield Solar Farmsolar farmsolar farm4.4operationalupdated Sep 2018Jun 2015granted Sep 2015Sep 2018Breckland6.2
Shipdham Wind Parkwind farmwind farm4.6refusedupdated Nov 2015Aug 2011refused Sep 2012Nov 2015Breckland6.5
The Park Farm, Birds Cornerbattery storagebattery storage800application submittedupdated Aug 2025Jun 2025—Aug 2025Breckland7.4
The Park Farm, Birds Cornersolar farmsolar farm49.9application submittedupdated Aug 2025Nov 2024—Aug 2025Breckland7.4
North Pickenham Airfieldwind farmwind farm4operationalupdated Mar 2015Sep 2009granted Sep 2010Mar 2015Breckland8.4
North Pickenhamwind farmwind farm14.4operationalupdated May 2009Mar 2004granted Oct 2004May 2009Breckland8.7
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Tesco Superstore Thetford Roadrooftop solarrooftop solar0.2operationalupdated Oct 2021Nov 2019granted Apr 2020Oct 2021Breckland2.0
Cranswick Country Foods, Brandon Roadrooftop solarrooftop solar0.7approved, not builtupdated Jan 2023Nov 2022granted Dec 2022Jan 2023Breckland3.0
Cranswick Country Foods, Abattoir Brandon Roadsolar farmsolar farm0.8approved, not builtupdated May 2026Dec 2025granted Mar 2026May 2026Breckland3.0
HMP Waylandsolar farmsolar farm0.3operationalupdated Mar 2022Mar 2022granted Apr 2022Mar 2022Breckland4.0
Lays Farm, Wood Lanerooftop solarrooftop solar0.2approved, not builtupdated Dec 2022Sep 2022granted Oct 2022Dec 2022Breckland9.3

Distance from the average position of the IP25 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm5122052.5
Rooftop solar302100.9
Wind farm300210
Battery storage11000800

MW in pipeline: pending, approved and under-construction capacity.

How Breckland decides solar, wind and battery applications

ApplicationsBrecklandUK
Decided applications (solar, wind, battery)3810,236
Refused7 (18%)19%
Solar refused4 of 2812%
Onshore wind refused3 of 745%
Battery storage refused0 of 316%
Median time from submission to decision19.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

All projects in Breckland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near IP25, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.