Energy Projects Near You

Walpole Bank (40 MW solar farm)

Walpole Bank is a 40 MW solar farm project in King's Lynn and West Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 28 October 2024; the record was last updated on 26 November 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
under constructionstatus in REPD
26 November 2024record last updated
King's Lynn and West Norfolkcouncil area

Planning timeline

DateStage
25 September 2020Application submitted
15 January 2021Planning permission granted
28 October 2024Construction started

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
under construction
Record last updated
26 November 2024
Operator or applicant
DIF Capital Partners / Green Investment Group
Planning authority
King's Lynn and West Norfolk
Planning application reference
20/01508/FM
Site area
56.0 ha
Address (REPD)
West & S/O Walpole Substation Walpole Bank, Walpole Marsh, Walpole St Andrew Wisbech
Council area (by location)
King's Lynn and West Norfolk
Time to decision
16 weeks
Contracts for Difference
AR4
REPD reference
9524

Who decides

ApplicationsKing's Lynn and West NorfolkUK
Decided applications (solar, wind, battery)6010,236
Refused11 (18%)19%
Solar refused5 of 3812%
Onshore wind refused3 of 645%
Battery storage refused3 of 1616%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Walpole St Andrewbattery storage100approved, not built0.5
Walpole Sub Station, Walpole Bankbattery storage100approved, not built0.5
Model Farmbattery storage49.9approved, not built0.7
Walpole Sub Station, Walpole Bankbattery storage100approved, not built0.7
Walpole Bankbattery storage100application submitted0.8
Rose And Crown Farmsolar farm30operational1.2
North Walpole, St Peterbattery storage100approved, not built1.5
Lapwing Fen II, Crown Farmbattery storage49.9approved, not built1.9
Lapwing Fen 2 Battery Storage Plantbattery storage250under construction1.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7226, 0.1993).