Energy Projects Near You

Lapwing Fen II, Crown Farm (49.9 MW battery storage)

Lapwing Fen II, Crown Farm is a 49.9 MW battery storage project in Fenland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 5 March 2020, not yet built; the record was last updated on 22 November 2022. REPD also records that the planning permission expired on 5 March 2023, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtmay be out of datestatus in REPD
22 November 2022record last updated
Fenlandcouncil area

REPD also records that the planning permission expired on 5 March 2023, so the project may not go ahead in this form.

Planning timeline

DateStage
25 November 2019Application submitted
5 March 2020Planning permission granted
5 March 2023Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
22 November 2022
Operator or applicant
Private Developer
Planning authority
King's Lynn and West Norfolk
Planning application reference
19/02002/FM
Address (REPD)
Crown Farm, Mill Road, West Walton, Wisbech,
Council area (by location)
Fenland
Time to decision
14 weeks
REPD reference
7606

Who decides

ApplicationsKing's Lynn and West NorfolkUK
Decided applications (solar, wind, battery)6010,236
Refused11 (18%)19%
Solar refused5 of 3812%
Onshore wind refused3 of 645%
Battery storage refused3 of 1616%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lapwing Fen 2 Battery Storage Plantbattery storage250under construction0.6
Model Farmbattery storage49.9approved, not built1.7
Walpole Banksolar farm40under construction1.9
Gunthorpe Road, Marsh Solar Farmsolar farm49.9approved, not built1.9
Rose And Crown Farmsolar farm30operational2.1
Walpole St Andrewbattery storage100approved, not built2.3
Walpole Sub Station, Walpole Bankbattery storage100approved, not built2.3
Walpole Sub Station, Walpole Bankbattery storage100approved, not built2.6
Walpole Bankbattery storage100application submitted2.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7233, 0.1713).